Data Centres Must Bring Their Own Power: What It Means for Sparkies

9 min readElectricalRoles.com.au
Data Centres Must Bring Their Own Power: What It Means for Sparkies

AirTrunk's 1 GW Hunter deal, NSW's hourly renewables push, SEC's Glenrowan battery and NZ solar: data centres must bring their own power. Here's the work.

When people talk about AI data centres, the conversation usually stops at the building: the halls of servers, the cooling, the giant substation out the back. What I find far more interesting for electricians is the shift that has happened in the last fortnight. Data centres in Australia are being told, more and more clearly, that they have to bring their own power. Not just buy certificates. Actually help get new solar farms, wind farms and batteries built and wired into the grid.

That is a big deal for anyone with a licence. Every megawatt a data centre has to "bring" is another project that needs cable pulled, inverters and battery enclosures terminated, protection tested and systems commissioned. Here's what happened in the first half of November, and what I think it means for your next few years of work.

AirTrunk lines up more than 1 GW in the Hunter

On 12 November, data centre operator AirTrunk signed an exclusivity agreement with European Energy Australia covering two projects in the Hunter-Central Coast Renewable Energy Zone: a 260 MW solar farm, more than 800 MWh of battery storage and a wind project of up to 350 MW, as Energy-Storage.news reported.

The two companies are now discussing a long-term power purchase agreement to supply AirTrunk's NSW load, including its proposed Kurri Kurri campus on the old Hydro Aluminium smelter site at Loxford. State planning records describe that campus at 550.5 MW of total power consumption. The solar and battery assets are expected to start operating in 2030 and the wind farm in 2032, connecting to Ausgrid's upgraded 132 kV network in the REZ, subject to approvals and final connection arrangements.

AirTrunk's founder Robin Khuda put it neatly: "Digital growth must bring new energy with it." The company has also said publicly that each extra gigawatt of data centre demand is likely to need around 3 to 4 GW of new renewable generation to run around the clock.

Sit with that number for a second. If data centre demand grows by even a few gigawatts, the generation, storage and network build that has to come with it is several times bigger. That's a long runway of work, and it sits squarely in the skill set of solar farm sparkies, HV electricians, cable jointers and commissioning techs.

Mulwala shows the model actually works

This isn't all paper. On 5 November, European Energy and AirTrunk officially opened the 31 MW Mulwala Solar Farm in southern NSW, which is now running at full output with most of its electricity going to AirTrunk. A 25 MW / 100 MWh battery is due to be added.

The numbers from that build are a nice reality check on what even a "small" project involves: construction started in September 2025, created more than 250 local jobs with the on-site workforce peaking at 73 a day, and took more than 40,000 working hours to install over 50,000 panels on almost 7,000 piles. Construction finished in March, it was energised the same month, and commissioning and testing ran through 2026.

That last bit is the part I'd underline for electricians. The panels go in fast. The energisation, testing and commissioning tail is where the specialist electrical skill lives, and it runs for months. Now scale Mulwala up roughly tenfold and you have the Hunter projects.

NSW wants hourly matching, not annual averages

The policy push behind all this got sharper on 5 November, when a NSW Legislative Council committee published its report into data centres. PV Tech's write-up covers the detail: 143 submissions, five public hearings and 26 recommendations. Recommendation 11 asks that data centres be legally required to supply their own 100% renewable energy on an hourly basis, at a minimum.

The current NSW Data Centre Guidelines, released in August, set a looser bar of an average 80% correlation between new supply and demand across a year. Under an hourly test, midday solar can't be counted against demand at 2am. It's a recommendation, not law, but it points in one direction. At the federal level, the Prime Minister said in July that large data centres would be legally required to put at least as much renewable energy into the grid as they draw, with legislation targeted for early 2027.

Here's why hourly matching matters to you. If you have to match every hour, solar alone doesn't cut it. You need batteries, wind and firming too. The inquiry noted that data centre power deals so far have tended to favour solar over the wind, storage and firming the grid needs. Hourly rules would tip the balance toward big batteries and hybrid sites, and those are exactly the projects that need skilled electrical crews for the longest.

The guidelines already require data centres to show they can cut grid demand by 25% of forecast average load for up to two hours using battery storage and load shifting, with diesel generators ruled out for that job. The committee also wants the state to reduce reliance on diesel backup and promote batteries and other behind-the-meter options. Translation: more battery rooms, more DC systems and more switchboards inside and around these campuses.

Some context on the scale, again from the inquiry: Ausgrid told the committee data centres are about 4% of NSW operational load today and could reach 17 to 30% by 2040. The Clean Energy Council, citing AEMO, said NSW data centre demand is set to grow fivefold by 2035. Not every proposed project will be built (one estimate quoted in the guidelines is that only around 20% of connection applications proceed), but even the realistic slice is enormous.

Victoria's SEC signs up a 102 MW battery at Glenrowan

Down south, state-owned SEC announced on 2 November that it had secured a 10-year offtake for a new 102 MW, four-hour battery at the Glenrowan Solar Farm in Victoria's north-east, owned by Pacific Partnerships. The battery is expected to go to construction after financial close, and it's the owner's first large-scale battery hybridisation of an operating solar farm.

I love this kind of project, because it's a template we'll see again and again: take a solar farm that's already running and bolt a battery onto it so the midday sunshine can be sold in the evening peak. SEC already supplies renewable electricity, backed by storage, to more than 4,400 sites across Victoria, around 5% of the state's demand. Hybridising existing solar farms is quicker than greenfield builds and it's prime work for battery and commissioning electricians in regional Victoria.

Ausgrid opens up its network data

On 12 November, Ausgrid released a digital energy mapping tool to support its Community Power Network trial, reported by pv magazine. The tool shows where there's spare capacity on the local network for more solar and batteries, where limits exist and where future energy projects might suit, across Mascot-Botany, the Northern Central Coast and Caringbah.

The idea of the trial is to use big commercial and industrial rooftops to generate more solar, back it with community batteries, and share the benefits with renters and apartment dwellers who can't put panels on their own roof.

This is the smaller-scale cousin of the data centre story, and it's brilliant news for commercial electricians. Warehouses and factory roofs around Mascot and Botany are some of the best solar real estate in Sydney. If the network data shows where systems will connect without being curtailed, more of those projects get the green light, and every one of them needs a commercial solar crew, a switchboard upgrade and often a battery.

Electrician connecting a new community battery beside a warehouse covered in rooftop solar in sunny Sydney

Across the Tasman: solar farms under Ruapehu

New Zealand's build keeps rolling too. The NZ Herald reported on 11 November on two major solar farms near construction at the foot of Ruapehu, off the Volcanic Loop Highway between Waiōuru and Ohakune: Harmony Energy's 156 MW Tangiwai Hybrid Solar Farm and the Karioi Solar Farm, now owned by Anza Power. Both will feed the grid through Transpower's Tangiwai substation. For Karioi, financial close is expected early next year, with construction expected to start in late 2027 and take about a year. A separate Marton solar farm of about 65 MW is also planned, connecting at Transpower's Marton substation.

For Kiwi sparkies and anyone in Australia eyeing a stint across the ditch, the central North Island is shaping up as a solar hub. Utility-scale solar experience travels well between our two countries, so the skills you build on a Queensland or NSW solar farm are directly useful there.

What I'd do with this if I were on the tools

Here's my honest read. The story of the next five years isn't "data centres versus the grid". It's data centres becoming one of the biggest customers paying for the grid to be built. That's an optimistic story, and it's one electricians are at the centre of.

A few practical moves I'd make:

  1. Get battery experience now. Hourly matching, demand-response requirements and hybridised solar farms all point to batteries. If you're a solar electrician, put your hand up for battery and BESS work at every chance you get.
  2. Learn to commission, not just install. Mulwala's months of testing and commissioning are the norm, not the exception. Testing, protection and commissioning skills are what make you hard to replace.
  3. Follow the REZs. The Hunter-Central Coast REZ, north-east Victoria and the central North Island are all getting busier. Regional work often pays more and comes with accommodation or living-away allowances.
  4. Don't overlook the commercial roof. Ausgrid's mapping tool is a signal that C&I solar and community batteries are going to keep growing in the suburbs. That's great work if you'd rather sleep in your own bed.
  5. Think about HV. A lot of this generation connects at 132 kV or above. HV switching, substation and cable jointing tickets are some of the best career investments in the trade right now.

I'll keep tracking these projects as they move from deals to diggers. When the contractors start hiring, the jobs will land on ElectricalRoles.com.au first. If you're ready for your next move, now is a great time to get your profile up to date.

The exponential age needs a lot of electrons, and every single one of them needs a sparky to get it where it's going. I can't think of a better trade to be in.

Industry NewsData CentresAIBatteriesBESSSolarWindDistributionCareersNew South WalesVictoriaNew ZealandAustralia
Free email alerts

Be the first to know.

New electrical jobs, employers and talent, straight to you as they go live. Stay in the loop.

Get the inside track →